Page 31
Demonstration Approval Period: October 1, 2024 through September 30, 2029 Page 31 of 43
X. SCHEDULE OF STATE DELIVERABLES DURING THE DEMONSTRATION
Deliverable Timeline STC Reference Quarterly Expenditures Reports Within 30 days following the end of each quarter using Form CMS-64 STC 38 Annual Monitoring Report Annual Deliverable – Due 90 calendar days following the end of each demonstration year STC 24
Draft Evaluation Design Within 180 calendar days after demonstration approval STC 54 Revised Evaluation Design Within 60 days following receipt of CMS comments on Draft Evaluation Design STC 55 Draft Interim Evaluation Report Within one year prior to the end of the demonstration or with submission of a demonstration extension request. STC 57 Revised Interim Evaluation Report Within 60 calendar days following receipt of CMS comments on the Draft Interim Evaluation Report. STC 57 Summative Evaluation Report Within 18 months following the end of the demonstration approval period identified in these STCs. STC 58 Revised Summative Evaluation Report Within 60 calendar days after receipt of CMS comments on the Draft Summative Evaluation Report. STC 58