Page 387
387 | P a g e FFY 2025–2027 CCDF State Plan
Appendix 1: Lead Agency Implementation Plan The Appendix will be available for Lead Agencies to use in CARS after the Plan approval letter is issued. For each non-compliance, Lead Agencies must describe the following: • Action Steps: List the action steps needed to correct the finding (e.g., update policy manual, legislative approval, IT system changes, etc.). For each action step list the: o Responsible Entity: Indicate the entity (e.g., agency, team, etc.) responsible for completing the action step. o Expected Completion Date: List the expected completion date for the action step. • Overall Target Date for Compliance: List date Lead Agency anticipates completing implementation, achieving full compliance with all aspects of the findings. (Note: Compliance will not be determined until the FFY 2025-2027 CCDF Plan is amended and approved).